Gate ME-2010 Question Paper With Solutions

Q 47. The project activities, precedence relationships and durations are described in the table. The critical path of the project is
Gate ME-2010 Question Paper With Solutions
(A) P-R-T -V

(B) Q-S -T -V

(C) P-R-U -W

(D) Q-S -U -W

Answer: (D)

Explanation:

Gate ME-2010 Question Paper With Solutions

Gate ME-2010 Question Paper With Solutions

Learn More:   Gate EC-2016 - 3 Question Paper With Solutions

LEAVE A REPLY

Please enter your comment!
Please enter your name here