Gate ME-2006 Question Paper With Solutions

Q 66. A manufacturing shop processes sheet metal jobs, wherein each job must pass through two machines (M1 and M2, in that order). The processing time (in hours) for these jobs is:
Gate ME-2006 Question Paper With Solutions

The optimal make-span (in hours) of the shop is:

(A) 120

(B) 115

(C) 109

(D) 79

Answer: (B)

Explanation:

Gate ME-2006 Question Paper With Solutions

Gate ME-2006 Question Paper With Solutions

Gate ME-2006 Question Paper With Solutions

Gate ME-2006 Question Paper With Solutions

Gate ME-2006 Question Paper With Solutions

Learn More:   Gate ME 2015-2 Question Paper With Solutions

LEAVE A REPLY

Please enter your comment!
Please enter your name here