Gate ME-2005 Question Paper With Solutions

Q 73. A project has six activities (A to F) with respective activity durations 7, 5, 6, 6, 8, 4 days. The network has three paths AB, CD and EF. All the activities can be crashed with the same crash cost per day. The number of activities that need to be crashed to reduce the project duration by 1 day is

(A) 1

(B) 2

(C) 3

(D) 6

Answer: (C)

Explanation:

Gate ME-2005 Question Paper With Solutions

Learn More:   Gate EE-2003 Question Paper With Solutions

LEAVE A REPLY

Please enter your comment!
Please enter your name here