Q 13.  Which one of the following is NOT a decision taken during the aggregate
production planning stage ?

(A) Scheduling of machines

(B) Amount of labour to be committed

(C) Rate at which production should happen

(D) Inventory to be carried forward

Answer: (A)

Explanation: