Gate EC-2016 – 2 Question Paper With Solutions

Q.5 S, M, E and F are working in shifts in a team to finish a project. M works with twice the efficiency of others but for half as many days as E worked. S and M have 6 hour shifts i a day, whereas E and F have 12 hours shifts. What
is the ratio of contribution of M to contribution of E in the project?

(A) 1 : 1

(B) 1 : 2

(C) 1 : 4

(D) 2 : 1

Answer: (B)

Explanation:

Gate EC-2016 - 2 Question Paper With Solutions

Learn More:   Gate CS-2017-1 Question Paper With Solutions

LEAVE A REPLY

Please enter your comment!
Please enter your name here