Gate ME 2014-4 Question Paper With Solutions

Q. 29 Demand during lead time with associated probabilities is shown below:

Gate ME 2014-4 Question Paper With Solutions
Expected demand during lead time is _____.

Answer: (74.55)

Explanation:

Gate ME 2014-4 Question Paper With Solutions

Learn More:   Gate CS-2004 Question Paper With Solutions

LEAVE A REPLY

Please enter your comment!
Please enter your name here