Q. 63 5 skilled workers can build a wall in 20 days: 8 semi-skilled workers can build a
wall in 25 days; 10 unskilled workers can build a wall in 30 days. If a team has 2
skilled, 6 semi-skilled and 5 unskilled workers, how long will it take to build the
wall?

(A) 20

(B) 18

(C) 16

(D) 15

Answer: (D)

Explanation: