Gate ME 2015-2 Question Paper With Solutions

Q. 64 A project consists of 7 activities. The network along with the time durations (in
days) for various activities is shown in the figure.
The minimum time (in days) for completion of the project is_______

Gate ME 2015-2 Question Paper With Solutions

Answer: (* )

Explanation:

Not Required.

Learn More:   Gate ME-2020-2 Question Paper With Solutions

LEAVE A REPLY

Please enter your comment!
Please enter your name here